The Build Season
Overview
- Now that you have a team structure in place, it’s time to get started
- For most of you, this is the largest project you have undertaken
- There is a hard deadline – Ship Date
- The only way to succeed is to manage your time effectively
Timeline - The Beginning
- Build season – 6 weeks and 3 days
- You must stay on schedule. There’s no time to fall behind
- Week 1
- Brainstorming – Days 1-4
- Design Freeze – Day 5
- Established robot design
- Mobility system frozen
- Frozen means no more changes!!
- General ideas for all mechanisms
- Mechanism Prototyping – Days 5-8
- Build Drive System – Days 5-14
Timeline – The Middle
- Week 2
- Mechanism Build – Days 8-21
- Programmers Begin Coding – Day 8
- Can & should start pseudo-coding earlier
- Robot Controls – Days 8-14
- Drive System Complete – Day 14
- Having the robot moving early is crucial!!
- Week 3
- Begin Autonomous Testing – Day 15
- Most FIRST autonomy only involve the chassis
Timeline – The End
- Week 4
- Mechanism Integration – Days 22-28
- Wiring is not a quick job
- Weeks 5-6
- Robot Done – Day 29
- Testing & Perfecting – Days 29-40
- Not as easy as it sounds
- Weight Reduction
- Driver Training – Days 29-40
- “Practiced drivers make bad robots win, and unpracticed drivers make good robots lose”
Timeline – Loose Ends
- The Last Few Days
- Decorations
- Parts Inventory
- Photographs
- Packing The Crate
- Celebration
- General Tips
- Perfectionism can kill the schedule
- “Never let perfectionism get in the way of getting a good job done”
- Your real lives are more important than FIRST!
- Your family and marks come FIRST!
- “All robots and no sleep make Johnny go crazy”